“ADDITIONAL WORK OF SCHOOL AND KINDERGARTEN COMPLEX OF KHANBOGD SOUM” PROJECT

“ADDITIONAL WORK OF SCHOOL AND KINDERGARTEN COMPLEX OF KHANBOGD SOUM” PROJECT

PROJECT RATIONALE:


Due to the incomplete heating system planning of the cultural hall, library and other rooms in construction drawing and budget of the “640-student school and 200-child kindergarten complex of Khanbogd soum”, newly constructed Khanbogd soum school and kindergarten were inadequately heated during the cold season. It was also necessary to ensure the school and kindergarten complex’s regular operation and create a comfortable learning environment, as the glass skylights would not be suitable for desert conditions if they were not replaced, rain and snow leak and disrupt the operation of the building.

 


PROJECT OBJECTIVE:

 

  • To solve the heating system of the cultural hall, library and other rooms.
  • To change and redesign the glass skylights to prevent water leakage during snow and rain.

 


PROJECT IMPLEMENTATION:

 

  • The additional work for heating, roof and glass skylight of Khanbogd soum School and kindergarten complex project was supported and approved by the resolution No.14 of the “Gobi oyu development support fund” Board on December 11, 2019.
  • The Owner, Umnugobi aimag Governor’s office has selected the contractor and executed a contract. The Umnugobi aimag Governor office, the contractor, “Binder altai oyu” LLC, and the “Gobi oyu development support fund” signed the tripartite financing agreement and commenced the project.
  • Heaters were installed in the rooms with no heaters of the 640-student school and 200-child kindergarten complex of Khanbogd soum, and its roof glass skylights were redesigned to prevent snow and rainwater runoff.
  • On August 10, 2020, the state commission finalized the project hand over.

 


OUTCOMES:

 

  • The learning and working conditions have improved for 280 children and 29 teachers and workers of Kindergarten No. 29, 708 students and 55 teachers and staff of School No.02 of Khanbogd soum.
  • The school and kindergarten complex heating problem is fully resolved.
  • Rain and snow water leakage is fully resolved and provided comfortable environment for students and workers of the school and kindergarten.